Development works are progressing well at Middlefields depot, with completion expected July 2020.

Progress includes:

  • Internal road diversions - Completed in October 2019
  • New Recycling Transfer Station - Construction started in November 2019 and is on programme
  • Re-roofing of the main depot - Ongoing and is on programme

The works are being carried out in phases to minimise disruption.

Latest updates

Road closure details and any changes of access within the Middlefields depot during these works will be communicated as soon as possible.

Please keep checking this page for updates.

For specific queries, please email middlefields.redevelopment@southtyneside.gov.uk

Last updated: 22 January 2020